Two Storms, Two Insurance Claims: How One Florida Gulf Coast Condominium Board Kept Every Scope and Signature Separate

"Keep us out of fiduciary trouble."
In the fall, a Florida Gulf Coast condominium community was hit twice.
The first storm brought flooding — into the clubhouse and into a group of residential units. Twelve days later the second storm arrived and did an entirely different kind of damage: trees, limbs and debris strewn across the common areas and the grounds.
Two storms. Two different perils. Two different insurance claims — one flood, one wind.
Lincoln Hancock Restoration did not roll them into one contract.
The first agreement was signed from two phones in under three hours.
Five days after the second storm, a debris-clearing agreement went to the board's treasurer, who opened it and signed from a phone. LHR's president countersigned from another. Sent, signed and executed the same morning.
The agreement is worth remembering for something other than its speed. It is worth remembering for what LHR refused to put in it.
LHR narrowed its own scope on purpose, and left the rest to the board.
LHR kept its own scope for debris removal and nothing else.
Pool restoration was on the table — equipment, repairs, cleaning, furniture. LHR did not add it. If the board wanted that work, it would have to ask in writing, as a separate decision made on the board's own timeline.
A full roof and exterior assessment — including drone footage, developed alongside the wind carrier's adjuster — was available too, at no charge. Also only if the board asked for it in writing. LHR named it, priced it at zero, and left it in the board's hands.
The agreement drew a hard line at the residents' front doors. No entering anyone's unit for water remediation unless the association specifically requested it in writing. No moving or handling anyone's personal belongings without that owner's written permission.
For volunteer board members who have to face their neighbors at the next meeting, that line matters as much as anything else in the document.
Then LHR told the board the thing that costs a contractor money to say.
Lincoln Hancock Restoration told the board that the debris work was probably not covered by their wind claim.
And then committed — in that same agreement — to documenting it as though it were. Hours worked. Unit pricing. Every vendor, subcontractor and disposal invoice. All of it turned over to the adjuster, with the stated goal of helping the association recover coverage it might not otherwise receive.
The billing matched the posture. Time and materials, with the actual invoices put in front of the board rather than summarized for them. The association's existing vendors were used wherever they were available. No service fees were charged to the association. Liens cleared at final payment, with lien releases delivered along the way instead of promised at the end.
The flood claim started with a question, not a construction contract.
The flood damage was a separate claim, so it took a separate path — and LHR did not ask the board to commit to construction in order to find out what construction would cost.
Instead LHR offered to answer one question for the board first: What does this repair actually cost? The clubhouse and the damaged units were scoped and estimated separately, each itemized line by line in Xactimate, the estimating platform the flood carrier works from.
The board reviewed LHR's proposal before the work began and approved the staffing plan before anyone was assigned to the job. LHR agreed in writing that the board was entitled to rely on the accuracy, completeness and timeliness of what it produced — and that anything found not to conform would be reported promptly.
And the board kept a clean exit. It could stop at any point before signing a construction contract, owing nothing beyond the estimating work already delivered.
That is an unusual thing to hand a board at the exact moment it has the least leverage.
LHR waited for the board's own vote before it countersigned.
When the repair contracts were ready, the board president signed — and the contract itself carried a note saying he still had to call a meeting of the board, that the board had to vote, and that the association would give LHR written notice of its acceptance or rejection.
LHR wrote that into its own contract. On the clubhouse work, LHR countersigned roughly three weeks later, after the board's process had run its course.
A contractor in a hurry doesn't do that. A contractor who understands what fiduciary duty actually costs a volunteer board does.
The homeowners were watching, and the contract said so.
The repair contracts committed LHR to daily cleanup, and to leaving the property clean when the work was done — tools, equipment, surplus material and debris gone. Payment applications went to the board and to the carrier at the same time. The board kept the right to bring in its own third-party inspector and to hold back payment for work that didn't meet the standard.
And in the clubhouse closeout documentation, every line was labeled by whether it fell inside the carrier's scope or outside it. Even at the end, the board could see exactly which dollars were insurance and which were the association's.
Two storms. Separate claims. Nothing bundled.
Separate perils. Separate scopes. Separate documentation. Separate decisions — and a volunteer board that knew exactly what it was authorizing, every single time it signed.
Keeping a board out of fiduciary trouble is not a promise a contractor makes. It is a paper trail a contractor leaves.
That is what integrity looks like when it's operational instead of aspirational.
This is LHR. Integrity in Action.
Questions Boards Ask About This Project
What happens if storm work isn't covered by our insurance claim?
Lincoln Hancock Restoration told this board the debris work likely fell outside the wind claim rather than letting the board discover it later. It then documented every hour, every unit price and every invoice for the adjuster anyway, so the association had the record either way.
Can a board find out what a repair costs before committing to construction?
On this project it did. Lincoln Hancock Restoration produced itemized estimates for the clubhouse and the damaged units first, and the board could stop at any point before signing a construction contract, owing nothing beyond the estimating work already delivered.
What stops a contractor from entering an owner's unit?
The written agreement. On this project it barred LHR from entering any unit for water remediation without a specific written request from the association, and from moving or handling any owner's belongings without that owner's written permission.
Next Steps
- If your board is about to authorize storm work it will have to defend later, tell us what happened and when you next meet. We will show you what the record should look like before you sign anything.
- Not in a loss right now? That is the best time to have this conversation. Ask us what your board should have documented before a storm, not after.
For storm claims like this one, we only work with community associations ready to build a record their board can defend.